View Issue Details

IDProjectCategoryView StatusLast Update
0002037T99X171.00 SKB EagleGeneralpublic2026-03-25 12:37
Reporter(ALTech) SH Son Assigned To(PM) Roisy Liang Due Date
PrioritynormalSeveritys4-minorReproducibilityhave not tried
Status closedResolutionfixed 
Summary0002037: [Eagle] 2025.03 Monthly RMA_KR (Lot 24) shipping list
Description[Eagle] 2025.03 Monthly RMA_KR (Lot 24) shipping list
TagsNo tags attached.
Attach Tags

Relationships

related to 0001690 new [Eagle] RMA status 
related to 0002036 closed(MFG) Rachel Ruan [EAGLE] 2025.03 Mass production inspection Report 

Activities

(ALTech) SH Son

2025-04-03 09:50

developer   ~0017395

Hi Roisy,

this is list of 2025.3 Monthly base RMA.
Please check and feedback within 2days
If there is no response within 2 days, this lot will be considered in of warranty.

Thanks
SON
image.png (19,022 bytes)   
image.png (19,022 bytes)   

(PM) Roisy Liang

2025-04-03 17:54

developer   ~0017397

Dear Mr.SON,

I would like to update warranty time as below: 71pcs in of warranty and 8pcs out of warranty. Please refer the attached file.
Let me know if you have any questions.

Thank you,
Roisy

(ALTech) SH Son

2025-04-14 15:30

developer   ~0017486

Hi Roisy,

update the list of 2025.3 Monthly base RMA.
Please check again and feedback within 2days


Thanks
image-2.png (20,560 bytes)   
image-2.png (20,560 bytes)   

(PM) Roisy Liang

2025-04-16 11:12

developer   ~0017489

Dear Mr.SON,

I would like to update warranty time as below: 153pcs in of warranty and 2pcs out of warranty. Please refer the attached file.
Let me know if you have any questions.

Thank you,
Roisy

(ALTech) SH Son

2025-04-17 07:39

developer   ~0017491

Hi Roisy

Thank you for the confirmation.

this lot will be ship out end of this month
I will update schedule and shipping documents.

Thanks
SON

(ALTech) SH Son

2025-04-22 15:14

developer   ~0017499

Hi Roisy

here is draft Invoice and shipping schedule

I will update BL soon.

Thanks
SON
image-3.png (9,656 bytes)   
image-3.png (9,656 bytes)   

(ALTech) SH Son

2025-04-28 12:47

developer   ~0017515

Hi Roisy

Here is draft BL

I will update final BL
Thanks
SON
FIHKG250168.pdf (309,981 bytes)

(ALTech) SH Son

2025-04-28 13:14

developer   ~0017516

here is final BL

Thanks
SON
FIHKG250168-2.pdf (310,532 bytes)

(ALTech) SH Son

2025-05-13 09:29

developer   ~0017542

Hi Roisy

Please update the Lot23&24 status

ETA Factory
ETD (after RMA) Factory

Thanks
SON

(PM) Roisy Liang

2025-05-21 12:08

developer   ~0017552

Dear Mr.SON,

Please help to check the status of lot 23&24 as below:
ETA Factory: 27th May
ETD(after RMA) Factory: 26th June

Thanks,
Roisy

(PM) Roisy Liang

2025-06-24 16:41

developer   ~0017601

Dear Mr.SON,

I am very regret when informing to you that: all end June of boats was full, and we only can return RMA lot 23&24 in early July. Now the forwarder is finding July boat, and I will update detail shipping plan to you as soon as receiving it.
Let me know if you have any questions.

Thanks,
Roisy

(PM) Roisy Liang

2025-06-27 12:20

developer   ~0017602

Dear Mr.SON,

I would like to send you FA and scrap report of RMA lot 23&24. Please kindly check the attached file and let me know if you have any questions.

Thanks,
Roisy

(ALTech) SH Son

2025-07-07 10:02

developer   ~0017606

Hi Roisy
confirm the FA and scrap report of RMA lot 23&24.
Please update shipping documents and shipping schedule


Thanks
SON

(PM) Roisy Liang

2025-07-09 10:58

developer   ~0017607

Dear Mr.SON,

This is invoice&packing list of lot 23&24 and the shipment will leave the factory by tomorrow. Shipping method: express shipment.
Please check the attached file.

Thanks
Roisy

(PM) Roisy Liang

2025-07-22 16:12

developer   ~0017616

Dear Mr.SON,

I would like to send you final HAWB for RMA lot 23&24. Please kindly check the attached file and let me know if you have any questions.

Thanks,
Roisy
45T0400224.pdf (88,319 bytes)

Issue History

Date Modified Username Field Change
2025-04-03 09:43 (ALTech) SH Son New Issue
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (ALTech) BY Lee
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (ALTech) JW Kim
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (ALTech) Lonnie Kim
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (ALTech) SH Son
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (ALTech) Sophie Lee
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (ALTech) SY Yoon
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (MFG) An Tran
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (PM) Roisy Liang
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (PM) Sheila Tu
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (PM) Tiffanie Lai
2025-04-03 09:43 (ALTech) SH Son Issue Monitored: (Sales) Miya Wang
2025-04-03 09:43 (ALTech) SH Son Relationship added related to 0001690
2025-04-03 09:43 (ALTech) SH Son Assigned To => (PM) Roisy Liang
2025-04-03 09:43 (ALTech) SH Son Status new => assigned
2025-04-03 09:44 (ALTech) SH Son Relationship added related to 0002036
2025-04-03 09:50 (ALTech) SH Son Note Added: 0017395
2025-04-03 09:50 (ALTech) SH Son File Added: 20250403_79PCS FORMAT RMA.xlsx
2025-04-03 09:50 (ALTech) SH Son File Added: image.png
2025-04-03 17:54 (PM) Roisy Liang Note Added: 0017397
2025-04-03 17:54 (PM) Roisy Liang File Added: 20250403_79PCS FORMAT RMA-2.xlsx
2025-04-07 09:24 (SW) Willin Deng Severity s2-severe => s4-minor
2025-04-14 15:30 (ALTech) SH Son Note Added: 0017486
2025-04-14 15:30 (ALTech) SH Son File Added: image-2.png
2025-04-14 15:30 (ALTech) SH Son File Added: 20250414_155PCS FORMAT RMA.xlsx
2025-04-16 11:12 (PM) Roisy Liang Note Added: 0017489
2025-04-16 11:12 (PM) Roisy Liang File Added: 20250414_155PCS FORMAT RMA-2.xlsx
2025-04-17 07:39 (ALTech) SH Son Note Added: 0017491
2025-04-22 15:14 (ALTech) SH Son Note Added: 0017499
2025-04-22 15:14 (ALTech) SH Son File Added: 20250422 BFX-AT100_Lot24_Invoice 선적서류.xls
2025-04-22 15:14 (ALTech) SH Son File Added: image-3.png
2025-04-28 12:47 (ALTech) SH Son Note Added: 0017515
2025-04-28 12:47 (ALTech) SH Son File Added: FIHKG250168.pdf
2025-04-28 13:14 (ALTech) SH Son Note Added: 0017516
2025-04-28 13:14 (ALTech) SH Son File Added: FIHKG250168-2.pdf
2025-05-13 09:29 (ALTech) SH Son Note Added: 0017542
2025-05-21 12:08 (PM) Roisy Liang Note Added: 0017552
2025-06-24 16:41 (PM) Roisy Liang Note Added: 0017601
2025-06-27 12:20 (PM) Roisy Liang Note Added: 0017602
2025-06-27 12:20 (PM) Roisy Liang File Added: FA report of 185pcs RMA T99X171.00 ver1.xlsx
2025-06-27 12:20 (PM) Roisy Liang File Added: 109pcs Scrap RMA T99X171.00.xlsx
2025-07-07 10:02 (ALTech) SH Son Note Added: 0017606
2025-07-09 10:58 (PM) Roisy Liang Note Added: 0017607
2025-07-09 10:58 (PM) Roisy Liang File Added: Invoice&packing list of 185pcs RMA T99X171 .xls
2025-07-22 16:12 (PM) Roisy Liang Note Added: 0017616
2025-07-22 16:12 (PM) Roisy Liang File Added: 45T0400224.pdf
2026-03-25 12:37 (ALTech) SH Son Status assigned => closed
2026-03-25 12:37 (ALTech) SH Son Resolution open => fixed